The Government accorded administrative approval for Rs.3500.00 Lakhs vide GO Ms No 38 I & CAD dated 07.03.2005 for Construction of Barrage. The estimate for civil works was technically sanctioned vide CE (I) No. 5/05-06, dt.04.04.2005 for Rs.18.80 Crores based on SSR 2004-05 as per the Drawings issued by CE, CDO. The work was entrusted to M/s JK Constructions, Hyderabad vide Agt.No.21SE/05-06, dt.09.01.2006 for Rs.18.36 Crores with stipulated period of completion 18 months i.e. by 08.07.2007.About 80% of civil works were completed except 7 road bridge slabs, and hoist piers, approach slab. Fabrication of gates is in progress.
Location | : | The Barrage is under construction across Muniyeru River near Pollampalli village of Vastavai mandal, Krishna District. |
Basin | : | Krishna |
Latitude | : | 17° 05' N |
Longitude | : | 80° 10' E |
Distance from Village/Town | : | 25 Km from Khammam, 210 Km from Hyderabad |
Catchment area in Sq.Km | : | 6111.91 |
Capacity | : | 800 Mcft at +71.000 FRL |
Utilization | : | 3500 Mcft |
Ayacut | : | 16,427 acres |
Under Left Main Canal:50 Km | : | 16,427 acres |
Vent Size & Nos | : | 1.88 m x 1.52 m & 4 |
Sill level | : | +65.26 |
Discharge in cumecs | : | 310 |
Maximum Flood Discharge | : | 1,00,000 Cusecs |
Spillway Details | ||
Type, Size &Nos | : | Anicut system |
Crest Level | : | +67.39 m |
TBL | : | Not Applicable |
Mandals benefited | : | Vatsavai, Penuganchiprolu, and Nandigama |
Assembly Constituency | : | Jaggaiahpet |
Parliament Constituency | : | Vijayawada |
The work is programmed to be complete by March, 2011.The mechanical works awarded to M/s Swapna Constructions on 2.3.2009 for an amount of Rs.15.88 Crores based on SSR 2008-09, with a programme of 9 months and the agreement was concluded.Total value of civil works: Rs.24.80 / 32.66 Crores (including price escalation).%of work done as on 02/ 2010: 80.72%.% of balance work is 19.28 %.
Budget | : | A Provision of 25.10 Crores is in BE 2011-12. |
Land acquisition | : | Nil |